[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915527":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915527,589,2,"多选题","下列关于隧道控制测量说法正确的是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","洞外平面控制测量可以使用GPS定位",true,{"key":16,"text":17,"correct":14},"B","洞外高程控制测量通常使用水准测量",{"key":19,"text":20,"correct":21},"C","洞内平面控制测量可以使用GPS定位",false,{"key":23,"text":24,"correct":21},"D","洞内高程控制测量通常使用三角高程测量",{"key":26,"text":27,"correct":14},"E","每个洞口应埋设不少于两个水准点，最好是一站可以观测这两点的高差","ABE","隧道控制测量基本知识：洞外平面控制测量可以使用GPS定位；洞外高程控制测量和洞内高程控制测量，通常使用水准测量；每个洞口应埋设不少于两个水准点，最好是一站可以观测这两点的高差；洞内不可能有GPS信号，故洞内无法使用GPS定位，选项C，描述不正确。洞内通常使用水准测量进行高程控制测量，选项D描述不正确。故选ABE。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]