[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915410":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915410,589,2,"多选题","（2011 年） 按现行《工程测量规范》 ， 变形测量过程中必须立即报告建设单位和施工单位， 采取相应安全措施的情况包括（） 。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","变形量达到预警值或接近允许值",true,{"key":16,"text":17,"correct":14},"B","变形量出现异常变化",{"key":19,"text":20,"correct":21},"C","少数变形观测点遭到破坏",false,{"key":23,"text":24,"correct":14},"D","建（构） 筑物或地表的裂缝快速扩大",{"key":26,"text":27,"correct":21},"E","数据处理结果不符合技术方案要求","ABD","本节 2.1（3） 中的内容。 每期观测结束后， 应及时处理观测数据，当数据处理结果出现下列情况之一时， 必须即刻通知建设单位和施工单位采取相应措施：①变形量达到预警值或接近允许值； ②变形量出现异常变化； ③建（构） 筑物的裂缝或地表的裂缝快速扩大。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]