[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915095":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},915095,589,1,"单选题","制作DEM格网点的高程赋值遇到河流时处理方式为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按上下游水位高程的平均高程处理",false,{"key":16,"text":17,"correct":18},"B","依照上下游水位高程分段内插处理",true,{"key":20,"text":21,"correct":14},"C","在高程空白区域格网赋予高程值－9999",{"key":23,"text":24,"correct":14},"D","按高程控制区处理分别赋予最大值最小值","根据《基础地理信息数字成果1∶500、1∶1000、1∶2000数字高程模型》（CH\u002FT 9008.2—2010）第6.5条和6.7条规定，静止水域范围内的DEM高程值应一致，其高程值应取常水位高程。流动水域内的DEM高程应自上而下平缓过渡，并且与周围地形高程之间的关系正确、合理。空白区域是指获取的数据源出现由于局部中断等原因无法获取高程的区域，位于空白区域的格网高程值应赋予－9999。根据规定，“流动水域内的DEM高程应自上而下平缓过渡”，即制作DEM格网点的高程赋值遇到河流时处理方式为依照上下游水位高程分段内插处理。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]