[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},914756,589,1,"单选题","建筑物沉降观测中，基准点数至少应有（ ）个",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","沉降观测是测量变形体在垂直方向上的位移。根据《工程测量规范》（GB 50026—2007）第10.1.4条第1款规定，变形监测网的网点，宜分为基准点、工作基点和变形观测点。其布设应符合下列要求：基准点应选在变形影响区域之外稳固可靠的位置。每个工程至少应有3个基准点。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]