[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},914747,589,1,"单选题","某地下管线测量项目共探查隐蔽管线点565个，根据现行《工程测量规范》，采用开挖验证方法进行质量检查，开挖验证的点数至少为（ ）个。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"根据《工程测量规范（附条文说明）》（GB 50026—2007）第7.2.6条对隐蔽管线的检查相关规定，开挖验证的点位应随机抽取，点数不宜少于隐蔽管线点总数的1%，且不应少于3个点。由于共探查隐蔽管线点565个且点数不可为小数，因此应取6个。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]