[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},914734,589,1,"单选题","现行《工程测量规范》规定，测绘1∶1000水下地形图利用GPS RTK方法进行平面定位时，流动站点相对于基准站点的作业半径最大不得超过（ ）km。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":14},"C","15",{"key":22,"text":23,"correct":24},"D","20",true,"根据《工程测量规范（附条文说明）》（GB 50026—2007）规定，GPS定位宜采用GPS-RTK或GPS-RTD（DGPS）方式；当定位精度符合工程要求时，也可采用后处理差分技术。参考占点位的选择和设置，应符合第5.3.13条和第5.3.14条的规定，作业半径可放宽至20km。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]