[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},914720,589,1,"单选题","某丘陵地区工程测量项目，利用GPS拟合高程测量方法建立五等高程控制网。按技术设计，将联测四等水准点5个，新设GPS高程点15个。根据现行《工程测量规范》，对GPS点的拟合高程成果应进行检测，检测点数不应少于（ ）个。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","5","根据《工程测量规范（附条文说明）》（GB 50026—2007）第4.4.5条规定，对GPS点的拟合高程成果应进行检测。检测点数不少于全部高程点的10%且不少于3个点；高差检验，可采用相应等级的水准测量方法或电磁波测距三角高程测量方法进行，其高差较差不应大于 mm（D为检查路线的长度，单位为km）。技术设计中共设置高程点20个，依据规范可知检测点数应不少于3个。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]