[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},914707,589,1,"单选题","某丘陵地区1∶1000地形测图基本等高距确定为1m，那么，图根控制点的高程相对于邻近等级控制点的中误差不应超过（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","±0.10",true,{"key":16,"text":17,"correct":18},"B","±0.15",false,{"key":20,"text":21,"correct":18},"C","±0.20",{"key":23,"text":24,"correct":18},"D","±0.25","根据《工程测量规范（附条文说明）》（GB 50026—2007）第5.2.1条规定，图根点平面控制和高程控制测量，可同时进行，也可分别施测。图根点相对于邻近等级控制点的点位中误差不应大于图上0.1mm，高程中误差不应大于基本等高距的1\u002F10。因此本题中图根控制点的高程相对于邻近等级控制点的中误差不应超过±1×1\u002F10＝±0.1（m）。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]