[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},914704,589,1,"单选题","施工放样工作总误差由控制点误差和放样作业误差两部分构成。按误差影响“忽略不计原则”，若放样作业误差为±18mm，当控制点误差最大为（ ）mm时，即可以认为其对施工放样的影响可忽略不计。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","±2",false,{"key":16,"text":17,"correct":14},"B","±3",{"key":19,"text":20,"correct":21},"C","±6",true,{"key":23,"text":24,"correct":14},"D","±9","设施工放样工作总误差M由控制点误差m1和放样作业误差m2两部分构成，按误差影响“忽略不计原则”，实际工作中一般取m1＝m2\u002F3＝±6mm。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]