[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},914701,589,1,"单选题","建筑物施工控制网坐标轴方向选择的基本要求是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","与国家统一坐标系方向一致",false,{"key":16,"text":17,"correct":14},"B","与所在城市地方坐标系方向一致",{"key":19,"text":20,"correct":21},"C","与设计所用的主副轴线方向一致",true,{"key":23,"text":24,"correct":14},"D","与正北、正东方向一致","根据《工程测量规范（附条文说明）》（GB 50026—2007）第8.1.6条规定，建筑物施工控制网，应根据场区控制网进行定位、定向和起算；控制网的坐标轴，应与工程设计所采用的主副轴线一致；建筑物的±0高程面，应根据场区水准点测设。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]