[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914678":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},914678,589,1,"单选题","利用航空摄影测量方法，对某一丘陵地区进行1:2000数字化测图，该区域的林地和阴影覆盖隐蔽区等困难区域的地物点平面中误差最大值为多少（ ）m。 A.±1.5 B.±1.8 C.±2.0 D.±2.5",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","平地、丘陵地地区地物点图上点位中误差为0.6 mm，林地和阴影覆盖隐蔽区等困难区域等放宽1\u002F2。该图上地物点平面中误差最大值为0.9mm，对应实地为1.8 m．",{"id":6,"name":25,"category":26,"favorite":27},"测绘综合能力","建筑工程",0]