[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},914603,589,1,"单选题","规范要求，用方向法进行水平角观测时，方向数超过3个应归零。“归零”是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","半测回结束前再观测一次起始方向",true,{"key":16,"text":17,"correct":18},"B","半测回结束后将度盘位置调到0°00′00″",false,{"key":20,"text":21,"correct":18},"C","一测回结束后将度盘位置调到0°00′00″",{"key":23,"text":24,"correct":18},"D","一测站结束前再观测一次起始方向","根据《工程测量规范》（GB 50026—2007）第3.3.8条规定，当观测方向不多于3个时，可不归零。“归零”是指半测回结束前再观测一次起始方向（零方向）。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]