[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},914575,589,1,"单选题","加密重力测量测线中，当仪器静放3小时以上时，必须在（ ）读数，按静态零漂计算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","静放前",false,{"key":16,"text":17,"correct":14},"B","静放后",{"key":19,"text":20,"correct":14},"C","静放中",{"key":22,"text":23,"correct":24},"D","静放前后",true,"根据《加密重力测量规范》（GB\u002FT 17944—2000）第5.3.7条规定，测线中仪器静放3小时以上时，必须在静放前后读数，按静态零漂计算。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]