[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914514":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},914514,589,1,"单选题","为求定GPS点在某一参考坐标系中的坐标，应与该参考坐标系中的原有控制点联测，联测的点数不得少于（ ）个点。 A．1 B．2 C．3 D．4",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","GPS大地控制网建设布设原则。GB\u002FT 18314-2009《全球定位系统(GPS)测量规范》6.1.5条规定对于新布设的GPS网应与附近已有的国家高等级GPS点进行联测，联测点数不应少于3点。",{"id":6,"name":25,"category":26,"favorite":27},"测绘综合能力","建筑工程",0]