[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-914082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},914082,589,1,"单选题","下列关于重力测量说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重力测量过程中，仪器停放超过2h，可以继续观测",true,{"key":16,"text":17,"correct":18},"B","一等重力点联测路线应组成闭合环或附合在两基本点间",false,{"key":20,"text":21,"correct":18},"C","二等重力点联测起算点为重力基本点、一等重力点或其引点",{"key":23,"text":24,"correct":18},"D","加密重力测量的重力测线应形成闭合或附合路线","重力测量过程中，仪器停放超过2h，应在停放点作重复观测，以消除静态零漂。故选A。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]