[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},913729,589,1,"单选题","根据《工程测量规范》有关建筑物施工放样的要求，已知某高层建筑物总高H=70m，其轴线竖向投测的偏差每层不应超过3mm，总偏差不应超过()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15mm",true,{"key":16,"text":17,"correct":18},"B","20mm",false,{"key":20,"text":21,"correct":18},"C","25mm",{"key":23,"text":24,"correct":18},"D","30mm","根据《工程测量规范》(GB50026—2007)第8.3.11条，建筑物施工放样应符合下列规定：建筑物施工放样、轴线投测和高程传递的偏差，不应超过表8.3.11的规定（见表3-9）。已知H=70m，对照该表，总偏差不应超过15mm。故选A。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]