[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},913728,589,1,"单选题","对于两开挖洞口间长度为6.4km的隧道工程，其相向施工中线在贯通面上的横向贯通误差不应大于()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","70mm",false,{"key":16,"text":17,"correct":14},"B","100mm",{"key":19,"text":20,"correct":21},"C","150mm",true,{"key":23,"text":24,"correct":14},"D","200mm","《工程测量规范》(GB50026—2007)第8.6.2条规定：隧道工程的贯通误差应符合表8.6.2的规定(注：规范中的表8.6.2可参看本书的表3-6)。对照该表，对于两开挖洞口间长度在4～8km之间的隧道工程，其相向施工中线在贯通面上的横向贯通误差不应大于150mm。故选C。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]