[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},913725,589,1,"单选题","根据《工程测量规范》，地下隧道在施工和运营初期，还应对受影响的地面建筑物、地表、地下管线等进行同步变形测量，并符合下列规定：新奥法隧道施工时，地表沉陷变形观测点，应沿隧道地面中线呈横断面布设，断面间距宜为10～50m，两侧的布点范围宜为隧道深度的()，每个横断面不少于5个变形观测点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.5倍",false,{"key":16,"text":17,"correct":18},"B","2.0倍",true,{"key":20,"text":21,"correct":14},"C","2.5倍",{"key":23,"text":24,"correct":14},"D","3.0倍","《工程测量规范》(GB50026—2007)第10.7.8条规定：新奥法隧道施工时，地表沉陷变形观测点，应沿隧道地面中线呈横断面布设，断面间距宜为10～50m，两侧的布点范围宜为隧道深度的2倍，每个横断面不少于5个变形观测点。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]