[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},913715,589,1,"单选题","下列不属于建设工程规划监督测量的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水准测量",true,{"key":16,"text":17,"correct":18},"B","放线测量",false,{"key":20,"text":21,"correct":18},"C","验收测量",{"key":23,"text":24,"correct":18},"D","验线测量","建设工程规划监督测量包括三个部分：①放线测量；②验线测量；③验收测量。故选A。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]