[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},913711,589,1,"单选题","根据《工程测量规范》(GB50026-2007)，全站仪测图的仪器安置及测站检核应符合下列要求：仪器的对中偏差不应大于5mm；应选择较远的图根点作为测站定向点，并施测另一图根点的坐标和高程，作为测站检核。检核点的平面位置较差不应大于图上()，高程较差不应大于基本等高距的1\u002F5。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.1mm",false,{"key":16,"text":17,"correct":18},"B","0.2mm",true,{"key":20,"text":21,"correct":14},"C","0.3mm",{"key":23,"text":24,"correct":14},"D","0.4mm","根据《工程测量规范》(GB50026—2007)第5.3.4条，全站仪测图的仪器安置及测站检核应符合下列要求：应选择较远的图根点作为测站定向点，并施测另一图根点的坐标和高程，作为测站检核；检核点的平面位置较差不应大于图上0.2mm，高程较差不应大于基本等高距的1／5。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]