[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},913705,589,1,"单选题","工程测量控制网可采用卫星定位测量方法。依照《工程测量规范》，对于GPS测量数据处理，其基线解算，应满足一定要求。下列选项中，描述错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","起算点的单点定位观测时间，不宜少于30min",false,{"key":16,"text":17,"correct":18},"B","解算模式不可采用单基线解算模式",true,{"key":20,"text":21,"correct":14},"C","解算模式可采用多基线解算模式",{"key":23,"text":24,"correct":14},"D","解算成果，应采用双差固定解","《工程测量规范》(GB50026—2007)第3.2.10条规定：对于GPS测量数据处理，其基线解算应满足下列要求：起算点的单点定位观测时间不宜少于30min；解算模式可采用单基线解算模式，也可采用多基线解算模式；解算成果，应采用双差固定解。选项B，描述错误。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]