[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},913702,589,1,"单选题","在环形粒子加速器工程施工中，为精确放样储能环上的磁块等设备，需要建立精密工程测量控制网。控制网可布设成()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","环形三角网",true,{"key":16,"text":17,"correct":18},"B","直伸形三角网",false,{"key":20,"text":21,"correct":18},"C","双大地四边形",{"key":23,"text":24,"correct":18},"D","双三角形","在环形粒子加速器工程施工中，为精确放样储能环上的磁块等设备，需要建立精密工程测量控制网。其精密工程测量控制网应布设成环形三角网。故选A。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]