[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},913654,589,1,"单选题","根据《工程测量规范》(GB50026—2007)，卫星定位测量控制网的布设应符合下列要求：控制网应由独立观测边构成一个或若干个闭合环或附合路线，各等级控制网中构成闭合环或附合路线的边数不宜多于()条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","8","根据《工程测量规范》(GB50026—2007)第3.2.4条，卫星定位测量控制网的布设应符合下列要求：控制网应由独立观测边构成一个或若干个闭合环或附合路线；各等级控制网中构成闭合环或附合路线的边数不宜多于6条。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]