[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},913641,589,1,"单选题","根据《工程测量规范》(GB50026—2007)中卫星定位测量的主要技术要求，四等的平均边长为2km，其约束平差后最弱边相对中误差的要求为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","≤1\u002F120000",false,{"key":16,"text":17,"correct":14},"B","≤1\u002F70000",{"key":19,"text":20,"correct":21},"C","≤1\u002F40000",true,{"key":23,"text":24,"correct":14},"D","≤1\u002F20000","《工程测量规范》(GB50026—2007)第3.2.1条规定：卫星定位测量控制网的主要技术要求，应符合表3.2.1的规定(见表3-8)。对照该表，“四等”，其约束平差后最弱边相对中误差的要求为≤1\u002F40000。故选C。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]