[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},913211,589,1,"单选题","（2012 年） 某地下管线测量项目共探查隐蔽管线点 565 个。 根据现行《工程测量规范》 ，采用开挖验证方法进行质量检查时， 开挖验证的点数至少为（） 个。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"本节 5.1 中的内容。 对隐蔽管线点探查结果， 应采用重复探查和开挖验证的方法进行质量检验。 重复探查的点位应随机抽取， 点数不宜少于探查点总数的 5%。开挖验证的点位应随机抽取， 点数不宜少于隐蔽管线点总数的 1%， 且不应少于 3 个",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]