[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},913173,589,1,"单选题","（2016 年） 工程控制网优化设计分为“零——三” 类， 其中“二类” 优化设计指（） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","网的精度设计",true,{"key":16,"text":17,"correct":18},"B","网的图形设计",false,{"key":20,"text":21,"correct":18},"C","网的基准设计",{"key":23,"text":24,"correct":18},"D","网的改进设计","本节 3.2 中的内容： 二类设计（精度设计） 是在控制网的网形和控制网成果要求精度已定的情况下， 设计各观测值的精度（权） ， 使观测工作量最佳分配。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]