[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},913078,589,1,"单选题","（2016 年） 若某工程施工放样的限差为±40mm， 则该工程的放样中误差最大为（）mm。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","±4",false,{"key":16,"text":17,"correct":14},"B","±10",{"key":19,"text":20,"correct":21},"C","±20",true,{"key":23,"text":24,"correct":14},"D","±40","限差为中误差的2倍。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]