[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},913072,589,1,"单选题","（2015 年） 沿附合水准路线测定 P 点高程如下， 则 P 点高程的最或然值是（） m。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","22.60",false,{"key":16,"text":17,"correct":14},"B","22.63",{"key":19,"text":20,"correct":21},"C","22.64",true,{"key":23,"text":24,"correct":14},"D","22.66","同第3题。B点观测高程为21.1+1.56-4.50=18.16，闭合差为18.16-18.1=0.06，P点高程为21.1+1.56-0.06\u002F6×2=22.64m。",{"id":6,"name":27,"category":28,"favorite":29},"测绘综合能力","建筑工程",0]