[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-913036":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},913036,588,2,"多选题","根据《测绘技术总结编写规定》，地理信息系统专业技术总结，开发工作评价的主要内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","生产效率的评价",true,{"key":16,"text":17,"correct":14},"B","产品质量的评价",{"key":19,"text":20,"correct":14},"C","技术方法的评价",{"key":22,"text":23,"correct":14},"D","出错原因的分析",{"key":25,"text":26,"correct":27},"E","系统集成基础软件的评价",false,"ABCD","开发工作评价的内容包括： ①对生产效率的评价。列出程序、文件的实际平均生产效率并与原定计划对比； ②对产品质量的评价。说明在测试中检查出来的错误发生率并与质量保证计划对比： ③对技术方法的评价。说明对开发中所使用的技术、方法、工具、手段的评价； ④出错原因的分析。分析开发过程中出现错误的原因。 E项，系统集成基础软件的评价不属于开发工作评价的主要内容。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]