[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912992,588,2,"多选题","测绘项目的人员配备分为项目负责人和以下哪些人员？（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","市场经营人员",false,{"key":16,"text":17,"correct":18},"B","生产管理人员",true,{"key":20,"text":21,"correct":18},"C","技术管理人员",{"key":23,"text":24,"correct":18},"D","质量控制人员",{"key":26,"text":27,"correct":18},"E","后勤保障人员","BCDE","测绘项目人员配置分为项目负责人、生产管理组、技术管理组、质量控制组、后勤服务部门。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]