[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912987":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912987,588,2,"多选题","下列选项中，影响测绘生产进度计划的因素有哪些？（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","测区气候变化的影响",true,{"key":16,"text":17,"correct":14},"B","技术设计变更",{"key":19,"text":20,"correct":14},"C","作业顺序调整",{"key":22,"text":23,"correct":14},"D","项目经费到位情况",{"key":25,"text":26,"correct":27},"E","甲方人事变动",false,"ABCD","影响生产进度完成计划的因素包括：①在估计项目的特点及项目实现的条件时，过高或过低地估计了有利因素。例如资金的保障情况、测区内的作业条件等；②在项目实施过程中各有关方面工作上的失误。例如项目委托方设计要求的变更、作业顺序的调整等；③不可预见事件的发生。不可预见事件包括政治、经济及自然等方面。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]