[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912985":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912985,588,2,"多选题","测绘项目的资源配置主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人员",true,{"key":16,"text":17,"correct":18},"B","资金",false,{"key":20,"text":21,"correct":14},"C","设备",{"key":23,"text":24,"correct":18},"D","耗材",{"key":26,"text":27,"correct":18},"E","技术","AC","人员和设备是完成测绘项目资源配置的两个主要条件，项目应配置合适的人员和设备。测绘项目人员配置分为项目负责人、生产管理组、技术管理组、质量控制组、后勤服务部门。目前测绘项目的主要设备包括水准仪、经纬仪、全站仪、GPS测量系统、航空摄影机、数字摄影测量工作站和数字成图系统等。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]