[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912752":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912752,588,2,"多选题","根据测绘法，测绘单位转包测绘项目应当承担的法律责任有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","责令改正",true,{"key":16,"text":17,"correct":14},"B","没收违法所得",{"key":19,"text":20,"correct":14},"C","处测绘约定报酬1倍以上2倍以下的罚款",{"key":22,"text":23,"correct":14},"D","可以责令停业整顿或者降低资质等级",{"key":25,"text":26,"correct":27},"E","情节严重的，吊销营业执照",false,"ABCD","根据《测绘法》第四十五条规定，测绘单位将测绘项目转包的，责令改正，没收违法所得，处测绘约定报酬1倍以上2倍以下的罚款，并可以责令停业整顿或者降低资质等级；情节严重的，吊销测绘资质证书，而非营业执照。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]