[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912738":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912738,588,2,"多选题","下列关于测绘项目承发包的说法中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包测绘项目的单位，可以借用其他单位设备、技术和劳力完成所承揽项目的主要部分",false,{"key":16,"text":17,"correct":18},"B","承包测绘项目的单位，不得将测绘项目转包",true,{"key":20,"text":21,"correct":18},"C","承包测绘项目的单位，可以将测绘项目分包，但分包量不大于总承包量的40%",{"key":23,"text":24,"correct":14},"D","承包测绘项目的单位将测绘项目分包的，由分包方向发包方负责",{"key":26,"text":27,"correct":18},"E","发包单位不得将测绘项目发包给不具有相应资质等级的单位","BCE","考核测绘法中有关测绘项目承发包的规定。项目发包单位不得将测绘项目发包给不具有相应测绘资质等级的单位。",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]