[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912678":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},912678,588,2,"多选题","（2016年）根据《测绘技术设计规定》，项目设计书对项目进度安排的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","划分作业区的困难类别",true,{"key":16,"text":17,"correct":18},"B","项目工程价格",false,{"key":20,"text":21,"correct":14},"C","根据设计方案分别计算统计各工序的工作量",{"key":23,"text":24,"correct":18},"D","说明计划投入的生产实力",{"key":26,"text":27,"correct":14},"E","参照有关生产定额， 分布列出年度进度计划和各工序衔接计划","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"测绘管理与法律法规","建筑工程",0]