[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},912506,588,1,"单选题","根据《测绘成果质量检查与验收》，在测绘项目成果最终检查过程中，对质量问题的判定存在分歧时，应由()裁定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目委托方",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","省级测绘产品质量监督检验机构",{"key":22,"text":23,"correct":24},"D","测绘单位总工程师",true,"根据《测绘成果质量检查与验收》4 . 6. 3 条款规定，过程检查、最终检查工作中，当对质量问题的判定存在分歧时，由测绘单位总工程师裁定。验收工作中，当对质量问题的判定存在分歧时，由委托方或项目管理单位裁定。故本题应选Do",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]