[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},912465,588,1,"单选题","下列有关“二级检查、一级验收”制度的说法正确的是哪一种？（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过程检查一般采用全数检查，最终检查一般采用全数检查，验收一般采用全数检查",false,{"key":16,"text":17,"correct":18},"B","过程检查一般采用全数检查，最终检查一般采用全数检查，验收一般采用抽样检查",true,{"key":20,"text":21,"correct":14},"C","过程检查一般采用全数检查，最终检查一般采用抽样检查，验收一般采用抽样检查",{"key":23,"text":24,"correct":14},"D","过程检查一般采用抽样检查，最终检查一般采用抽样检查，验收一般采用抽样检查","根据《测绘成果质量检查与验收》（GB\u002FT 24356-2009）第4.1条规定，“二级检查、一级验收”中，过程检查采用全数检查，最终检查一般采用全数检查，验收一般采用抽样检查，各级检查验收工作应独立、按顺序进行，最终检查应审核过程检查记录，验收应审核最终检查记录，审核中发现的问题作为资料质量错漏处理。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]