[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912464":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},912464,588,1,"单选题","测绘单位应当在关键工序、重点工序设置必要的（ ），实施工序产品质量的现场检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制点",false,{"key":16,"text":17,"correct":18},"B","检验点",true,{"key":20,"text":21,"correct":14},"C","间歇点",{"key":23,"text":24,"correct":14},"D","过度点","根据《测绘成果质量检查与验收》（GB\u002FT 24356—2009）相关规定，测绘单位应当在关键工序、重点工序设置必要的检验点。实施现场检查。现场检验点的设置，由测绘单位自行确定。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]