[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},912430,588,1,"单选题","关于测绘项目技术设计文件实施条件的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","报项目委托单位备案",false,{"key":16,"text":17,"correct":18},"B","报项目委托单位审批",true,{"key":20,"text":21,"correct":14},"C","报项目设计负责人审批",{"key":23,"text":24,"correct":14},"D","报项目承担单位批准","《测绘技术设计规定》5. 6 条款规定，技术设计文件编写完成后，承担测绘任务的法人单位必须对其进行全面审核，并签署意见，签名(或章) ;并一式二至四份报测绘任务的委托单位审批。据题意，本题答案应选B 。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]