[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},912419,588,1,"单选题","（ ）就是按照时间工序和工作性质，将项目分解为若干工序，也称子项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目工序",true,{"key":16,"text":17,"correct":18},"B","项目目标",false,{"key":20,"text":21,"correct":18},"C","工程分解",{"key":23,"text":24,"correct":18},"D","工程流程","项目工序就是按照时间工序和工作性质，将项目分解为若干工序，也称子项目。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]