[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},912415,588,1,"单选题","（ ）就是在项目合同规定的时间内完成整个项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期目标",true,{"key":16,"text":17,"correct":18},"B","质量目标",false,{"key":20,"text":21,"correct":18},"C","成本目标",{"key":23,"text":24,"correct":18},"D","管理目标","工期目标就是在项目合同规定的时间内完成整个项目。工期目标可分解为各个工序的工期目标。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]