[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},912371,588,1,"单选题","根据《测绘合同》示范文本，甲方按约定结清全部工程费用后，乙方应当按照()向甲方交付全部测量成果。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术设计书要求",true,{"key":16,"text":17,"correct":18},"B","测绘技术标准要求",false,{"key":20,"text":21,"correct":18},"C","测绘法律法规要求",{"key":23,"text":24,"correct":18},"D","技术总结说明","考核《测绘合同》的主要内容和项目管理能力。测绘项目合同中对应当提交的全部测量成果都应当有明确的界定。甲方按约定结清全部工程费用后，乙方应当按照技术设计书要求向甲方交付全部测量成果。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]