[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-912370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},912370,588,1,"单选题","决定测绘项目设备资源配置方案的主要因素不包括()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","测区状况",false,{"key":16,"text":17,"correct":14},"B","作业方法",{"key":19,"text":20,"correct":14},"C","项目工期",{"key":22,"text":23,"correct":24},"D","合同价款",true,"该题目考核项目管理能力。决定测绘项目设备资游、配置的主要因素，包括项目的工期、技术路线和作业方法，甚至要考虑测区的基本情况，合同价款只能作为参考，不是主要因素。",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]