[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-911457":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},911457,588,1,"单选题","（2013年）下列项目中，不属于测绘项目承担单位项目目标管理内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本目标",false,{"key":16,"text":17,"correct":14},"B","工期目标",{"key":19,"text":20,"correct":14},"C","质量目标",{"key":22,"text":23,"correct":24},"D","投资目标",true,"",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]