[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-911438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},911438,588,1,"单选题","（2012年）技术总结编写完成后，单位（ ）应对技术总结编写的客观性、完整性等进行审查进行并签字，并对技术总结编写的质量负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","法人",false,{"key":16,"text":17,"correct":14},"B","最高管理者",{"key":19,"text":20,"correct":14},"C","生产主管领导",{"key":22,"text":23,"correct":24},"D","总工程师或技术负贵人",true,"",{"id":6,"name":27,"category":28,"favorite":29},"测绘管理与法律法规","建筑工程",0]