[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-587-23":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":536},{"id":5,"name":6,"category":7,"favorite":8},587,"建设工程造价管理","建筑工程",0,23,50,2821,[13,34,46,58,70,82,94,106,118,129,140,148,157,169,179,189,197,209,217,225,237,249,257,264,276,284,296,308,316,323,335,346,354,366,378,390,397,407,419,431,438,445,454,461,473,485,492,504,512,524],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},909181,1,"单选题","某工程按全等节拍流水组织施工，共分4道施工工序，3个施工段，估计工期为72天，则其流水节拍应为（）天。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","6",false,{"key":24,"text":25,"correct":22},"B","9",{"key":27,"text":28,"correct":29},"C","12",true,{"key":31,"text":32,"correct":22},"D","18","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":24,"analysis":33},909182,"某工程组织成倍节拍流水施工，4个施工段，4个施工过程的流水节拍分别为5，10，10，15，则该工程的流水工期为（）天。",[38,40,42,44],{"key":20,"text":39,"correct":22},"50",{"key":24,"text":41,"correct":29},"55",{"key":27,"text":43,"correct":22},"60",{"key":31,"text":45,"correct":22},"70",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":27,"analysis":33},909183,"计划工期与计算工期相等的双代号网络计划中，某工作的开始节点和完成节点均为关键节点时，说明该工作（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"一定是关键工作",{"key":24,"text":53,"correct":22},"总时差为零",{"key":27,"text":55,"correct":29},"总时差等于自由时差",{"key":31,"text":57,"correct":22},"自由时差为零",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},909184,"某工程的双代号网络计划如下图所示（单位：天），该网络计划的关键线路为（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":22},"①—③—⑤—⑥",{"key":24,"text":65,"correct":29},"①—③—④—⑤—⑥",{"key":27,"text":67,"correct":22},"①—②—③—④—⑤—⑥",{"key":31,"text":69,"correct":22},"①—②—③—⑤—⑥",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":27,"analysis":33},909185,"关于关键路线，下列说法错误的是（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"在双代号时标网络中，从起始节点到终止节点，自始至终不出现波形线的是关键路线",{"key":24,"text":77,"correct":22},"在双代号网络图中，关键路线是工作持续时间最长的路线",{"key":27,"text":79,"correct":29},"关键路线上如果总时差为零，自由时差可以不为零",{"key":31,"text":81,"correct":22},"在单代号网络图中，从起始节点到终止节点，所有工作之间的时间间隔为零的线路为关键线路",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":24,"analysis":33},909186,"单代号网络计划中，关键线路是指（ ）的线路。",[86,88,90,92],{"key":20,"text":87,"correct":22},"由关键工作组成",{"key":24,"text":89,"correct":29},"相邻两项工作之间时间间隔均为零",{"key":27,"text":91,"correct":22},"由关键节点组成",{"key":31,"text":93,"correct":22},"相邻两项工作之间间歇时间均相等",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":27,"analysis":33},909187,"某工程双代号网络计划如下图所示，其中关键线路有（ ）条。",[98,100,102,104],{"key":20,"text":99,"correct":22},"1",{"key":24,"text":101,"correct":22},"2",{"key":27,"text":103,"correct":29},"3",{"key":31,"text":105,"correct":22},"4",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":31,"analysis":33},909188,"在某工程双代号网络计划中，工作N的最早开始时间和最迟开始时间分别为第20天和第25天，其持续时间为9天。该工作有两项紧后工作，它们的最早开始时间分别为第32天和第34天，则工作N的总时差和自由时差分别为（ ）天。",[110,112,114,116],{"key":20,"text":111,"correct":22},"3和0",{"key":24,"text":113,"correct":22},"3和2",{"key":27,"text":115,"correct":22},"5和0",{"key":31,"text":117,"correct":29},"5和3",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":20,"analysis":33},909189,"已知 A、B工作的紧后工作为 C，持续时间分别为11天、15天、19天， A、B工作最早开始时间分别为第18天、14天，C工作的最迟完成时间为第49天，则A工作的最迟开始时间应为（ ）天。",[122,124,126,127],{"key":20,"text":123,"correct":29},"19",{"key":24,"text":125,"correct":22},"21",{"key":27,"text":32,"correct":22},{"key":31,"text":128,"correct":22},"30",{"id":130,"libraryId":5,"type":15,"typeLabel":16,"stem":131,"options":132,"answer":24,"analysis":33},909190,"A、B工作完成后C工作开始，C工作完成后 D、E两项工作开始。已知 A、 B、 C、 D、E五项工作持续时间分别为3天、2天、4天，3天、5天， A、B工作最早开始时间分别为第8天、12天， D、E工作最迟完成时间分别为第25天、26天，则A工作的最迟开始时间应为（ ）天。",[133,135,137,138],{"key":20,"text":134,"correct":22},"11",{"key":24,"text":136,"correct":29},"14",{"key":27,"text":123,"correct":22},{"key":31,"text":139,"correct":22},"17",{"id":141,"libraryId":5,"type":15,"typeLabel":16,"stem":142,"options":143,"answer":20,"analysis":33},909191,"某工程双代号时标网络计划如下图所示，其中工作A的总时差为（ ）周。",[144,145,146,147],{"key":20,"text":99,"correct":29},{"key":24,"text":101,"correct":22},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":149,"libraryId":5,"type":15,"typeLabel":16,"stem":150,"options":151,"answer":24,"analysis":33},909192,"已知甲、乙工作结束后丙工作开始，三项工作的持续时间分别为5天、7天、9天，甲、乙工作最早开始时间分别为第12天、11天，丙工作最迟完成时间为第29天，则甲工作的自由时差应为（ ）天。",[152,154,155,156],{"key":20,"text":153,"correct":22},"O",{"key":24,"text":99,"correct":29},{"key":27,"text":101,"correct":22},{"key":31,"text":103,"correct":22},{"id":158,"libraryId":5,"type":15,"typeLabel":16,"stem":159,"options":160,"answer":20,"analysis":33},909193,"关于网络图绘制规则，说法错误的是（ ）。",[161,163,165,167],{"key":20,"text":162,"correct":29},"双代号网络图中的虚箭线严禁交叉，否则容易引起混乱",{"key":24,"text":164,"correct":22},"双代号网络图中严禁出现循环回路，否则容易造成逻辑关系混乱",{"key":27,"text":166,"correct":22},"双代号时标网络计划中的虚工作可用波形线表示自由时差",{"key":31,"text":168,"correct":22},"单代号搭接网络图中相邻两工作的搭接关系可表示在箭线上方",{"id":170,"libraryId":5,"type":15,"typeLabel":16,"stem":171,"options":172,"answer":31,"analysis":33},909194,"已知某工作总时差为8天，最迟完成时间为第16天，最早开始时间为第7天，则该工作的持续时间为（ ）天。",[173,175,177,178],{"key":20,"text":174,"correct":22},"8",{"key":24,"text":176,"correct":22},"7",{"key":27,"text":105,"correct":22},{"key":31,"text":99,"correct":29},{"id":180,"libraryId":5,"type":15,"typeLabel":16,"stem":181,"options":182,"answer":31,"analysis":33},909195,"已知 A、B工作的紧后工作为 C、 D，其持续时间分别为3天、4天、2天、5天。 A、B工作的最早开始时间为第6天、4天，则D工作的最早完成时间为（ ）天。",[183,185,186,188],{"key":20,"text":184,"correct":22},"10",{"key":24,"text":134,"correct":22},{"key":27,"text":187,"correct":22},"13",{"key":31,"text":136,"correct":29},{"id":190,"libraryId":5,"type":15,"typeLabel":16,"stem":191,"options":192,"answer":20,"analysis":33},909196,"已知A工作的紧后工作为 B、C （B、C的紧前工作只有 A），持续时间分别为8天、7天、4天。A工作的最早开始时间为第9天。 B、C工作的最迟完成时间分别为第37天、39天，则A工作的自由时差应为（ ）天。",[193,194,195,196],{"key":20,"text":153,"correct":29},{"key":24,"text":99,"correct":22},{"key":27,"text":187,"correct":22},{"key":31,"text":32,"correct":22},{"id":198,"libraryId":5,"type":15,"typeLabel":16,"stem":199,"options":200,"answer":20,"analysis":33},909197,"在工程网络计划中，关键线路是指（ ）。",[201,203,205,207],{"key":20,"text":202,"correct":29},"单代号网络计划中总的工作持续时间最长的线路",{"key":24,"text":204,"correct":22},"双代号网络计划中由关键节点组成的线路",{"key":27,"text":206,"correct":22},"单代号搭接网络计划中总的工作持续时间最长的线路",{"key":31,"text":208,"correct":22},"双代号时标网络计划中无虚箭线的线路",{"id":210,"libraryId":5,"type":15,"typeLabel":16,"stem":211,"options":212,"answer":24,"analysis":33},909198,"某工程双代号时标网络计划如下图所示（单位：周），则在不影响总工期的前提下，工作E可以利用的机动时间为（ ）周。",[213,214,215,216],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":29},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":218,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":219,"answer":24,"analysis":33},909199,[220,221,222,223],{"key":20,"text":101,"correct":22},{"key":24,"text":103,"correct":29},{"key":27,"text":105,"correct":22},{"key":31,"text":224,"correct":22},"5",{"id":226,"libraryId":5,"type":15,"typeLabel":16,"stem":227,"options":228,"answer":31,"analysis":33},909200,"某工程双代号网络计划如下图所示。当计划工期等于计算工期时，工作D的自由时差和总时差分别是（ ）。",[229,231,233,235],{"key":20,"text":230,"correct":22},"2和2",{"key":24,"text":232,"correct":22},"1和2",{"key":27,"text":234,"correct":22},"0和2",{"key":31,"text":236,"correct":29},"0和1",{"id":238,"libraryId":5,"type":15,"typeLabel":16,"stem":239,"options":240,"answer":20,"analysis":33},909201,"（ ）是指在双代号网络计划中，以该节点为开始节点的各项工作的最早开始时间。",[241,243,245,247],{"key":20,"text":242,"correct":29},"节点最早时间",{"key":24,"text":244,"correct":22},"节点开始时间",{"key":27,"text":246,"correct":22},"最早开始时间",{"key":31,"text":248,"correct":22},"节点最迟时间",{"id":250,"libraryId":5,"type":15,"typeLabel":16,"stem":251,"options":252,"answer":20,"analysis":33},909202,"某工程双代号网络计划中，工作N两端节点的最早时间和最迟时间如下图所示，则工作N总时差为（ ）。",[253,254,255,256],{"key":20,"text":105,"correct":29},{"key":24,"text":99,"correct":22},{"key":27,"text":101,"correct":22},{"key":31,"text":103,"correct":22},{"id":258,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":259,"answer":20,"analysis":33},909203,[260,261,262,263],{"key":20,"text":99,"correct":29},{"key":24,"text":101,"correct":22},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":265,"libraryId":5,"type":15,"typeLabel":16,"stem":266,"options":267,"answer":31,"analysis":33},909205,"工程网络计划费用优化的基本思路是，在网络计划中，当有多条关键线路时，应通过不断缩短（ ）的关键工作持续时间来达到优化目的。",[268,270,272,274],{"key":20,"text":269,"correct":22},"直接费总和最大",{"key":24,"text":271,"correct":22},"组合间接费用率最小",{"key":27,"text":273,"correct":22},"间接费总和最大",{"key":31,"text":275,"correct":29},"组合直接费用率最小",{"id":277,"libraryId":5,"type":15,"typeLabel":16,"stem":278,"options":279,"answer":31,"analysis":33},909206,"某工程网络计划中，工作D有两项紧后工作，最早开始时间分别为17和20，工作D的最早开始时间为12，持续时间为3，则工作D的自由时差为（ ）。",[280,281,282,283],{"key":20,"text":224,"correct":22},{"key":24,"text":105,"correct":22},{"key":27,"text":103,"correct":22},{"key":31,"text":101,"correct":29},{"id":285,"libraryId":5,"type":15,"typeLabel":16,"stem":286,"options":287,"answer":27,"analysis":33},909207,"工程网络计划资源优化的目的是通过改变（ ），使资源按照时间的分布符合优化目标。",[288,290,292,294],{"key":20,"text":289,"correct":22},"工作间逻辑关系",{"key":24,"text":291,"correct":22},"工作的持续时间",{"key":27,"text":293,"correct":29},"工作的开始时间和完成时间",{"key":31,"text":295,"correct":22},"工作的资源强度",{"id":297,"libraryId":5,"type":15,"typeLabel":16,"stem":298,"options":299,"answer":27,"analysis":33},909208,"A工作后有紧后工作 B、 C，它们的持续时间分别为5d、4d和6d； B、C工作最迟完成时间分别为25d和23d，则A工作的最迟开始时间为（ ）。",[300,302,304,306],{"key":20,"text":301,"correct":22},"4d",{"key":24,"text":303,"correct":22},"8d",{"key":27,"text":305,"correct":29},"12d",{"key":31,"text":307,"correct":22},"16d",{"id":309,"libraryId":5,"type":15,"typeLabel":16,"stem":310,"options":311,"answer":24,"analysis":33},909211,"在网络计划中，A工作的总时差为3天，A共有3个紧后工作 B、 C、 D，工作B的最早开工时间和最迟开工时间分别为第21天和第22天，工作C的最早完工时间和最迟完工时间分别为第23天和第25天，工作D的最早开工时间和最迟开工时间分别为第21天和第23天，则工作A的自由时差为（）天。",[312,313,314,315],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":29},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":317,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":318,"answer":24,"analysis":33},909212,[319,320,321,322],{"key":20,"text":105,"correct":22},{"key":24,"text":103,"correct":29},{"key":27,"text":101,"correct":22},{"key":31,"text":99,"correct":22},{"id":324,"libraryId":5,"type":15,"typeLabel":16,"stem":325,"options":326,"answer":31,"analysis":33},909213,"某分部工程双代号网络图如下图所示，图中不存在错误的是（ ）。",[327,329,331,333],{"key":20,"text":328,"correct":22},"存在循环回路",{"key":24,"text":330,"correct":22},"节点编号有误",{"key":27,"text":332,"correct":22},"存在多个起点节点",{"key":31,"text":334,"correct":29},"存在多个终点节点",{"id":336,"libraryId":5,"type":15,"typeLabel":16,"stem":337,"options":338,"answer":31,"analysis":33},909214,"双代号时标网络计划中，不能从图上直接识别的非关键工作的时间参数是（）。",[339,340,342,344],{"key":20,"text":246,"correct":22},{"key":24,"text":341,"correct":22},"最早完成时间",{"key":27,"text":343,"correct":22},"自由时差",{"key":31,"text":345,"correct":29},"总时差",{"id":347,"libraryId":5,"type":15,"typeLabel":16,"stem":348,"options":349,"answer":31,"analysis":33},909215,"某工程网络计划中工作B的持续时间为5天，其两项紧前工作的最早完成时间分别为第6天和第8天，则工作B的最早完成时间为第（ ）天。",[350,351,352,353],{"key":20,"text":21,"correct":22},{"key":24,"text":174,"correct":22},{"key":27,"text":134,"correct":22},{"key":31,"text":187,"correct":29},{"id":355,"libraryId":5,"type":15,"typeLabel":16,"stem":356,"options":357,"answer":27,"analysis":33},909216,"某工程双代号时标网络计划如下图所示，其中工作E的自由时差为（ ）。",[358,360,362,364],{"key":20,"text":359,"correct":22},"0周",{"key":24,"text":361,"correct":22},"1周",{"key":27,"text":363,"correct":29},"2周",{"key":31,"text":365,"correct":22},"3周",{"id":367,"libraryId":5,"type":15,"typeLabel":16,"stem":368,"options":369,"answer":31,"analysis":33},909217,"某工程双代号时标网络计划如下图所示，根据第6周末实际进度检查结果绘制的前锋线，下列描述正确的是（ ）。",[370,372,374,376],{"key":20,"text":371,"correct":22},"C工作实际进度拖后2周，影响工期2周",{"key":24,"text":373,"correct":22},"D工作实际进度超前2周，不影响工期",{"key":27,"text":375,"correct":22},"E工作实际进度拖后1周，不影响工期",{"key":31,"text":377,"correct":29},"E工作实际进度拖后1周，影响总工期1周",{"id":379,"libraryId":5,"type":15,"typeLabel":16,"stem":380,"options":381,"answer":31,"analysis":33},909218,"下列关于单代号网络图与双代号网络图绘制规则的区别的说法中正确的是（ ）。",[382,384,386,388],{"key":20,"text":383,"correct":22},"双代号网络图中严禁出现从一个节点出发，顺箭头方向又回到原出发点的循环回路，单代号网络图可以这样绘制",{"key":24,"text":385,"correct":22},"双代号网络图中的箭线应保持自左向右的方向，单代号网络图中的箭线可以逆向",{"key":27,"text":387,"correct":22},"双代号网络图中严禁出现双向箭头和无箭头的连线，单代号网络图则可以这样绘制",{"key":31,"text":389,"correct":29},"在绘制单代号网络图时，当网络图中有多项开始工作时，应增设一项虚拟的工作(S)，作为该网络图的起点节点",{"id":391,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":392,"answer":27,"analysis":33},909219,[393,394,395,396],{"key":20,"text":75,"correct":22},{"key":24,"text":77,"correct":22},{"key":27,"text":79,"correct":29},{"key":31,"text":81,"correct":22},{"id":398,"libraryId":5,"type":15,"typeLabel":16,"stem":399,"options":400,"answer":24,"analysis":33},909220,"在不影响其紧后工作最早开始时间的前提下，本工作可利用的机动时间为（ ）。",[401,402,403,405],{"key":20,"text":345,"correct":22},{"key":24,"text":343,"correct":29},{"key":27,"text":404,"correct":22},"最迟开始时间",{"key":31,"text":406,"correct":22},"最迟完成时间",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":20,"analysis":33},909221,"在按工作计算法计算双代号网络计划时间参数的过程中，网络计划的计算工期应当等于（ ）。",[411,413,415,417],{"key":20,"text":412,"correct":29},"以网络计划终点节点为完成节点的工作的最早完成时间的最大值",{"key":24,"text":414,"correct":22},"紧前工作最早完成时间的最大值",{"key":27,"text":416,"correct":22},"网络计划终点节点的最早时间",{"key":31,"text":418,"correct":22},"网络计划终点节点的最迟时间",{"id":420,"libraryId":5,"type":15,"typeLabel":16,"stem":421,"options":422,"answer":31,"analysis":33},909222,"在（ ）中，虚拟工作只能出现在网络图的起点节点和终点节点处。",[423,425,427,429],{"key":20,"text":424,"correct":22},"双代号网络图",{"key":24,"text":426,"correct":22},"双代号时标网路图",{"key":27,"text":428,"correct":22},"不存在",{"key":31,"text":430,"correct":29},"单代号网络图",{"id":432,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":433,"answer":31,"analysis":33},909223,[434,435,436,437],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":22},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":29},{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":251,"options":440,"answer":20,"analysis":33},909224,[441,442,443,444],{"key":20,"text":105,"correct":29},{"key":24,"text":99,"correct":22},{"key":27,"text":101,"correct":22},{"key":31,"text":103,"correct":22},{"id":446,"libraryId":5,"type":15,"typeLabel":16,"stem":447,"options":448,"answer":27,"analysis":33},909225,"A工作后有紧后工作 B、 C，它们的持续时间分别为5天、4天和6天； B、C工作最迟完成时间分别为25天和23天，则A工作的最迟开始时间为（ ）天。",[449,450,451,452],{"key":20,"text":105,"correct":22},{"key":24,"text":174,"correct":22},{"key":27,"text":28,"correct":29},{"key":31,"text":453,"correct":22},"16",{"id":455,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":456,"answer":20,"analysis":33},909226,[457,458,459,460],{"key":20,"text":99,"correct":29},{"key":24,"text":101,"correct":22},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":462,"libraryId":5,"type":15,"typeLabel":16,"stem":463,"options":464,"answer":20,"analysis":33},909227,"工程网络计划费用优化的目的是为了寻求（ ）。",[465,467,469,471],{"key":20,"text":466,"correct":29},"按要求工期寻求最低成本的计划安排",{"key":24,"text":468,"correct":22},"工期固定条件下的工程费用均衡安排",{"key":27,"text":470,"correct":22},"工程总成本固定条件下的最短工期安排",{"key":31,"text":472,"correct":22},"工期最短条件下的最低工程总成本安排",{"id":474,"libraryId":5,"type":15,"typeLabel":16,"stem":475,"options":476,"answer":31,"analysis":33},909228,"工程网络计划的工期优化是通过（ ），使计算工期满足要求工期。",[477,479,481,483],{"key":20,"text":478,"correct":22},"改变关键工作之间的逻辑关系",{"key":24,"text":480,"correct":22},"将关键工作压缩成非关键工作",{"key":27,"text":482,"correct":22},"压缩直接费最小的工作的持续时间",{"key":31,"text":484,"correct":29},"压缩关键工作的持续时间",{"id":486,"libraryId":5,"type":15,"typeLabel":16,"stem":239,"options":487,"answer":20,"analysis":33},909229,[488,489,490,491],{"key":20,"text":242,"correct":29},{"key":24,"text":244,"correct":22},{"key":27,"text":246,"correct":22},{"key":31,"text":248,"correct":22},{"id":493,"libraryId":5,"type":15,"typeLabel":16,"stem":494,"options":495,"answer":24,"analysis":33},909230,"某工程的双代号网络计划如下图所示(单位：天)，该网络计划的关键线路为（ ）。",[496,498,500,502],{"key":20,"text":497,"correct":22},"①→③→⑤→⑥",{"key":24,"text":499,"correct":29},"①→③→④→⑤→⑥",{"key":27,"text":501,"correct":22},"①→②→③→④→⑤→⑥",{"key":31,"text":503,"correct":22},"①→②→③→⑤→⑥",{"id":505,"libraryId":5,"type":15,"typeLabel":16,"stem":506,"options":507,"answer":24,"analysis":33},909231,"某分部工程单代号网络计划如下图所示，节点中下方数字为该工作的持续时间(单位：天)，其关键线路有（）条。",[508,509,510,511],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":29},{"key":27,"text":103,"correct":22},{"key":31,"text":105,"correct":22},{"id":513,"libraryId":5,"type":15,"typeLabel":16,"stem":514,"options":515,"answer":24,"analysis":33},909232,"根据《标准施工招标文件》，下列合同文件的内容不一致时，除专用合同条款另有约定外，应以（ ）为准。",[516,518,520,522],{"key":20,"text":517,"correct":22},"投标函",{"key":24,"text":519,"correct":29},"中标通知书",{"key":27,"text":521,"correct":22},"专用合同条款",{"key":31,"text":523,"correct":22},"通用合同条款",{"id":525,"libraryId":5,"type":15,"typeLabel":16,"stem":526,"options":527,"answer":24,"analysis":33},909233,"根据《标准施工招标文件》，除专用合同条款另有约定外，解释合同文件包括：①技术标准和要求；②图纸；③中标通知书；④投标函及投标函附录；⑤合同协议书。以上解释合同文件的优先顺序为（）。",[528,530,532,534],{"key":20,"text":529,"correct":22},"⑤—①—②—④—③",{"key":24,"text":531,"correct":29},"⑤—③—④—①—②",{"key":27,"text":533,"correct":22},"③—④—⑤—②—①",{"key":31,"text":535,"correct":22},"⑤—②—③—①—④",[537,540,543,546,549,552],{"id":15,"name":538,"category":7,"favorite":539},"领导干部任职前廉政法规知识测试题",92,{"id":541,"name":542,"category":7,"favorite":15},595,"建筑结构与设备",{"id":544,"name":545,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":547,"name":548,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":550,"name":551,"category":7,"favorite":8},534,"BIM工程师",{"id":553,"name":551,"category":7,"favorite":8},535]