[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-587-13":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":611},{"id":5,"name":6,"category":7,"favorite":8},587,"建设工程造价管理","建筑工程",0,13,50,2821,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,262,270,282,294,306,318,330,342,354,366,378,390,402,414,426,438,450,462,474,486,494,506,518,527,539,551,563,575,587,599],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},908661,1,"单选题","某施工企业向银行借款100 万元，年利率8%，半年复利计息一次，第三年末还本付息，则到期时企业需偿还银行（ ）万元。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","124.00",false,{"key":24,"text":25,"correct":22},"B","125.97",{"key":27,"text":28,"correct":29},"C","126.53",true,{"key":31,"text":32,"correct":22},"D","158.69","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},908662,"现有甲和乙两个项目，静态投资回收期分别为4 年和6 年，该行业的基准投资回收期为5 年。关于这两个项目的静态投资回收期的说法，正确的是（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":29},"甲项目的静态投资回收期只考虑了前4 年的投资效果",{"key":24,"text":41,"correct":22},"乙项目考虑全寿命周期各年的投资效果确定静态投资回收期为6 年",{"key":27,"text":43,"correct":22},"甲项目投资回收期小于基准投资回收期，据此可以准确判断甲项目可行",{"key":31,"text":45,"correct":22},"乙项目的资本周转速度比甲项目更快",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},908663,"下列影响因素中，用来确定基准收益率的基本因素是（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":29},"资金成本和机会成本",{"key":24,"text":53,"correct":22},"机会成本和投资风险",{"key":27,"text":55,"correct":22},"投资风险和通货膨胀",{"key":31,"text":57,"correct":22},"通货膨胀和资金成本",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},908664,"关于内部收益率的说法，正确的是（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":29},"内部收益率大于基准收益率时，投资方案在经济上可以接受",{"key":24,"text":65,"correct":22},"内部收益率是一个事先确定的基准折现率",{"key":27,"text":67,"correct":22},"内部收益率受项目外部参数的影响较大",{"key":31,"text":69,"correct":22},"独立方案用内部收益率评价与净现值评价，结论通常不一致",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},908665,"采用增量投资内部收益率（△IRR）法比选计算期不同的互斥方案时，对于已通过绝对效果检验的投资方案，确定优选方案的准则是（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"△IRR 大于基准收益率时，选择初始投资额小的方案",{"key":24,"text":77,"correct":29},"△IRR 大于基准收益率时，选择初始投资额大的方案",{"key":27,"text":79,"correct":22},"无论△IRR 是否大于基准收益率，均选择初始投资额小的方案",{"key":31,"text":81,"correct":22},"无论△IRR 是否大于基准收益率，均选择初始投资额大的方案",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":24,"analysis":33},908666,"某项目有甲、乙、丙三个投资方案，各方案的投资额及内部收益率见下表。若已知基准折现率为10%，则各方案净现值由大到小排序为（ ）。",[86,88,90,92],{"key":20,"text":87,"correct":22},"甲，乙，丙",{"key":24,"text":89,"correct":29},"乙，甲，丙",{"key":27,"text":91,"correct":22},"乙，丙，甲",{"key":31,"text":93,"correct":22},"丙，乙，甲",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":24,"analysis":33},908667,"某项目总投资为2500 万元，其中债务资金为800 万元，项目运营期内年平均净利润为200 万元，年平均息税为20 万元，则该项目的资本金净利润率为（ ）。",[98,100,102,104],{"key":20,"text":99,"correct":22},"10.0%",{"key":24,"text":101,"correct":29},"11.76%",{"key":27,"text":103,"correct":22},"13.3%",{"key":31,"text":105,"correct":22},"14.7%",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":27,"analysis":33},908668,"某项目建设总投资为6000 万元，项目投产期年息税前利润为900 万元，达到设计生产能力的正常年份年息税前利润为1200 万元，则该项目的总投资收益率为（ ）。",[110,112,114,116],{"key":20,"text":111,"correct":22},"24.00%",{"key":24,"text":113,"correct":22},"17.50%",{"key":27,"text":115,"correct":29},"20.00%",{"key":31,"text":117,"correct":22},"15.00%",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":27,"analysis":33},908669,"某技术方案总投资1500 万元，其中资本金1000 万元，运营期年平均利息18 万元，年平均所得税40.5 万元。若项目总投资收益率为12%，则项目资本金净利润率为（ ）。",[122,124,126,128],{"key":20,"text":123,"correct":22},"16.20%",{"key":24,"text":125,"correct":22},"13.95%",{"key":27,"text":127,"correct":29},"12.15%",{"key":31,"text":129,"correct":22},"12.00%",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":24,"analysis":33},908670,"某投资方案计算期现金流量如下表，该投资方案的静态投资回收期为（ ）年。",[134,136,138,140],{"key":20,"text":135,"correct":22},"2.143",{"key":24,"text":137,"correct":29},"3.125",{"key":27,"text":139,"correct":22},"3.143",{"key":31,"text":141,"correct":22},"4.125",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":27,"analysis":33},908671,"对于特定的投资方案，若基准收益率增大，则投资方案评价指标的变化规律是（ ）。",[146,148,150,152],{"key":20,"text":147,"correct":22},"净现值与内部收益率均减小",{"key":24,"text":149,"correct":22},"净现值与内部收益率均增大",{"key":27,"text":151,"correct":29},"净现值减小，内部收益率不变",{"key":31,"text":153,"correct":22},"净现值增大，内部收益率减小",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":20,"analysis":33},908672,"某投资方案建设期为1 年，第1 年年初投资8000 万元，第2 年年初开始运营，运营期为4 年，运营期每年年末净收益为3000 万元，净残值为零。若基准收益率为10%，则该投资方案的净现值和静态投资回收期分别为（ ）。",[158,160,162,164],{"key":20,"text":159,"correct":29},"645 万元和3.67 年",{"key":24,"text":161,"correct":22},"1510 万元和3.67 年",{"key":27,"text":163,"correct":22},"1510 万元和2.67 年",{"key":31,"text":165,"correct":22},"645 万元和2.67 年",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":24,"analysis":33},908673,"对于寿命期不同的互斥方案进行经济评价时，可以采用的动态评价方法是（ ）。",[170,172,174,176],{"key":20,"text":171,"correct":22},"增量投资收益率法和增量投资回收期法",{"key":24,"text":173,"correct":29},"研究期法和增量内部收益率法",{"key":27,"text":175,"correct":22},"净现值法和内部收益率法",{"key":31,"text":177,"correct":22},"净现值率法和内部收益率法",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":27,"analysis":33},908674,"某工程施工有两个技术方案可供选择，甲方案投资180 万元，年生产成本为45 万元，乙方案需投资220 万元，年生产成本为40 万元．设基准投资收益率为12% ，若采用增量投资收益率评价两方案，则（ ）。",[182,184,186,188],{"key":20,"text":183,"correct":22},"甲方案优于乙方案",{"key":24,"text":185,"correct":22},"甲乙两个方案的效果相同",{"key":27,"text":187,"correct":29},"乙方案优于甲方案",{"key":31,"text":189,"correct":22},"甲乙两个方案的折算费用相同",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":20,"analysis":33},908675,"某工程有甲乙丙丁四个实施方案可供选择，四个方案的投资额依次是60 万元、80 万元、100 万元、120 万元。年运行成本依次是16 万元、13 万元、10 万元和6 万元，各方案应用环境相同。设基准投资率为10%。则采用折算费用法选择的最优方案为（ ）。",[194,196,198,200],{"key":20,"text":195,"correct":29},"丁",{"key":24,"text":197,"correct":22},"甲",{"key":27,"text":199,"correct":22},"乙",{"key":31,"text":201,"correct":22},"丙",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":27,"analysis":33},908677,"某技术方案，年设计生产能力为8 万台，年固定成本为100 万元，单位产品售价为50 元，单位产品变动成本为售价的55%，单位产品销售税金及附加为售价的5%，则达到盈亏平衡点时的生产能力利用率为（ ）。",[206,208,210,212],{"key":20,"text":207,"correct":22},"55.50%",{"key":24,"text":209,"correct":22},"60.00%",{"key":27,"text":211,"correct":29},"62.50%",{"key":31,"text":213,"correct":22},"41.67%",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":31,"analysis":33},908678,"价值工程应用中，采用0-4 评分法确定的产品各部件功能得分见下表，则部件Ⅱ的功能重要性系数是（ ）。",[218,220,222,224],{"key":20,"text":219,"correct":22},"0.125",{"key":24,"text":221,"correct":22},"0.150",{"key":27,"text":223,"correct":22},"0.250",{"key":31,"text":225,"correct":29},"0.275",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":24,"analysis":33},908679,"价值工程应用中，如果评价对象的价值系数Ｖ＜1，则正确的改进方向是（ ）。",[230,232,234,236],{"key":20,"text":231,"correct":22},"剔除不必要功能或降低现实成本",{"key":24,"text":233,"correct":29},"剔除过剩功能及降低现实成本",{"key":27,"text":235,"correct":22},"不作为价值工程改进对象",{"key":31,"text":237,"correct":22},"提高现实成本或降低功能水平",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":27,"analysis":33},908680,"某公司生产单一产品，设计年生产能力为3 万件，单位产品的售价为380 元\u002F件，单位产品可变成本为120 元\u002F件，单位产品税金及附加为70 元\u002F件，年固定成本为285 万元。该公司盈亏平衡点的产销量为（ ）件。",[242,244,246,248],{"key":20,"text":243,"correct":22},"20000",{"key":24,"text":245,"correct":22},"19000",{"key":27,"text":247,"correct":29},"15000",{"key":31,"text":249,"correct":22},"7500",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":31,"analysis":33},908681,"通过应用价值工程优化设计，使某房屋建筑主体结构工程达到了缩小结构构件几何尺寸，增加使用面积，降低单方造价的效果。该提高价值的途径是（ ）。",[254,256,258,260],{"key":20,"text":255,"correct":22},"功能不变的情况下降低成本",{"key":24,"text":257,"correct":22},"成本略有提高的同时大幅提高功能",{"key":27,"text":259,"correct":22},"成本不变的条件下提高功能",{"key":31,"text":261,"correct":29},"提高功能的同时降低成本",{"id":263,"libraryId":5,"type":15,"typeLabel":16,"stem":264,"options":265,"answer":31,"analysis":33},908682,"暂无",[266,267,268,269],{"key":20,"text":20,"correct":22},{"key":24,"text":24,"correct":22},{"key":27,"text":27,"correct":22},{"key":31,"text":31,"correct":29},{"id":271,"libraryId":5,"type":15,"typeLabel":16,"stem":272,"options":273,"answer":27,"analysis":33},908683,"不同行业的投资项目，资本金占总投资的比例不同，其中，总投资是指（ ）。",[274,276,278,280],{"key":20,"text":275,"correct":22},"固定资产投资",{"key":24,"text":277,"correct":22},"固定资产投资加流动资金",{"key":27,"text":279,"correct":29},"固定资产投资加铺底流动资金",{"key":31,"text":281,"correct":22},"投资者投入的资金",{"id":283,"libraryId":5,"type":15,"typeLabel":16,"stem":284,"options":285,"answer":20,"analysis":33},908684,"既有法人筹措新建项目资本金时，下列项目资本金来源中，属于外部资金来源的是（ ）。",[286,288,290,292],{"key":20,"text":287,"correct":29},"企业增资扩股",{"key":24,"text":289,"correct":22},"企业银行存款",{"key":27,"text":291,"correct":22},"企业资产变现",{"key":31,"text":293,"correct":22},"企业产权转让",{"id":295,"libraryId":5,"type":15,"typeLabel":16,"stem":296,"options":297,"answer":27,"analysis":33},908685,"与发行股票相比，发行债券融资的优点是（ ）。",[298,300,302,304],{"key":20,"text":299,"correct":22},"企业财务负担小",{"key":24,"text":301,"correct":22},"企业经营灵活性高",{"key":27,"text":303,"correct":29},"便于调整资本结构",{"key":31,"text":305,"correct":22},"筹资成本较高",{"id":307,"libraryId":5,"type":15,"typeLabel":16,"stem":308,"options":309,"answer":24,"analysis":33},908687,"某企业从银行借款1000 万元，年利息120 万元，手续费等筹资费用30 万元，企业所得税率25%，该项借款的资金成本率为（ ）。",[310,312,314,316],{"key":20,"text":311,"correct":22},"9.00%",{"key":24,"text":313,"correct":29},"9.28%",{"key":27,"text":315,"correct":22},"11.25%",{"key":31,"text":317,"correct":22},"12%",{"id":319,"libraryId":5,"type":15,"typeLabel":16,"stem":320,"options":321,"answer":20,"analysis":33},908688,"关于项目资本金性质或特征的说法，正确的是（ ）。",[322,324,326,328],{"key":20,"text":323,"correct":29},"项目资本金是权益性资金",{"key":24,"text":325,"correct":22},"项目法人承担项目资本金的利息",{"key":27,"text":327,"correct":22},"投资者不可转让其出资",{"key":31,"text":329,"correct":22},"投资者可以任何方式抽回其出资",{"id":331,"libraryId":5,"type":15,"typeLabel":16,"stem":332,"options":333,"answer":24,"analysis":33},908689,"根据《外商投资产业指导目录》，必须由中方控股的项目是（ ）。",[334,336,338,340],{"key":20,"text":335,"correct":22},"综合影剧院项目",{"key":24,"text":337,"correct":29},"综合水利枢纽项目",{"key":27,"text":339,"correct":22},"超大型公共建设项目",{"key":31,"text":341,"correct":22},"农业深加工项目",{"id":343,"libraryId":5,"type":15,"typeLabel":16,"stem":344,"options":345,"answer":31,"analysis":33},908692,"下列融资成本中，属于资金使用成本的是（ ）",[346,348,350,352],{"key":20,"text":347,"correct":22},"发行手续费",{"key":24,"text":349,"correct":22},"担保费",{"key":27,"text":351,"correct":22},"资信评估费",{"key":31,"text":353,"correct":29},"债劵利息",{"id":355,"libraryId":5,"type":15,"typeLabel":16,"stem":356,"options":357,"answer":24,"analysis":33},908693,"某企业发行优先股股票，票面额的正常市价计算为500 万元，筹资费费率为4%，年股息率为10%，企业所得税率为25%，则其资金成本率为（ ）。",[358,360,362,364],{"key":20,"text":359,"correct":22},"7.81%",{"key":24,"text":361,"correct":29},"10.42%",{"key":27,"text":363,"correct":22},"11.50%",{"key":31,"text":365,"correct":22},"14.00%",{"id":367,"libraryId":5,"type":15,"typeLabel":16,"stem":368,"options":369,"answer":27,"analysis":33},908694,"某企业账面反映的长期资金4000 万元，其中优先股1200 万元，应付长期债券2800 万元。发行优先股的筹资费费率3% ，年股息率9%；发行长期债券的票面利率7% ，筹资费费率5% ，企业所得税率25% ，则该企业的加权平均资金成本率为（ ）。",[370,372,374,376],{"key":20,"text":371,"correct":22},"3.96%",{"key":24,"text":373,"correct":22},"6.11%",{"key":27,"text":375,"correct":29},"6.65%",{"key":31,"text":377,"correct":22},"8.15%",{"id":379,"libraryId":5,"type":15,"typeLabel":16,"stem":380,"options":381,"answer":24,"analysis":33},908695,"下列项目融资工作中，属于融资结构设计阶段工作内容的是（ ）",[382,384,386,388],{"key":20,"text":383,"correct":22},"进行融资谈判",{"key":24,"text":385,"correct":29},"评价项目风险因素",{"key":27,"text":387,"correct":22},"选择项目融资方式",{"key":31,"text":389,"correct":22},"组织贷款银团",{"id":391,"libraryId":5,"type":15,"typeLabel":16,"stem":392,"options":393,"answer":20,"analysis":33},908697,"在缴纳教育费附加的时候，其计税依据是以纳税人实际缴纳的（ ）之和。",[394,396,398,400],{"key":20,"text":395,"correct":29},"增值税、营业税、消费税",{"key":24,"text":397,"correct":22},"营业税、消费税、所得税",{"key":27,"text":399,"correct":22},"营业税、增值税、城市维护建设税",{"key":31,"text":401,"correct":22},"消费税、所得税、城市维护建设税",{"id":403,"libraryId":5,"type":15,"typeLabel":16,"stem":404,"options":405,"answer":27,"analysis":33},908698,"投保安装工程一切险时，安装施工用机械设备的保险金额应按（ ）计算",[406,408,410,412],{"key":20,"text":407,"correct":22},"实际价值",{"key":24,"text":409,"correct":22},"损失价值",{"key":27,"text":411,"correct":29},"重置价值",{"key":31,"text":413,"correct":22},"账面价值",{"id":415,"libraryId":5,"type":15,"typeLabel":16,"stem":416,"options":417,"answer":20,"analysis":33},908699,"关于中华人民共和国境内用人单位投保工伤保险的说法，正确的是（ ）。",[418,420,422,424],{"key":20,"text":419,"correct":29},"需为本单位全部职工缴纳工伤保险费",{"key":24,"text":421,"correct":22},"只需为与本单位订有书面劳动合同的职工投保",{"key":27,"text":423,"correct":22},"只需为本单位的长期用工缴纳工伤保险费",{"key":31,"text":425,"correct":22},"可以只为本单位危险作业岗位人员投保",{"id":427,"libraryId":5,"type":15,"typeLabel":16,"stem":428,"options":429,"answer":24,"analysis":33},908700,"根据《关于工伤保险率问题的通知》，建筑业用人单位缴纳工伤保险费最高可上浮到本行业基准率的（ ）。",[430,432,434,436],{"key":20,"text":431,"correct":22},"120%",{"key":24,"text":433,"correct":29},"150%",{"key":27,"text":435,"correct":22},"180%",{"key":31,"text":437,"correct":22},"200%",{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":440,"options":441,"answer":24,"analysis":33},908701,"下列关于增值税计算的说法正确的是（ ）。",[442,444,446,448],{"key":20,"text":443,"correct":22},"采用一般计税方法时，建筑业增值税税额为完税造价×10%",{"key":24,"text":445,"correct":29},"采用一般计税方法时，税前造价各费用项目均以不包含增值税可抵扣进项税额的价格计算",{"key":27,"text":447,"correct":22},"采用简易计税方法时，税前造价各费用项目均以不包含增值税可抵扣进项税额的价格计算",{"key":31,"text":449,"correct":22},"采用简易计税方法时，建筑业增值税税额为完税造价×3%",{"id":451,"libraryId":5,"type":15,"typeLabel":16,"stem":452,"options":453,"answer":31,"analysis":33},908702,"对于安装工程一切险的保险期限的说法，正确的是（ ）。",[454,456,458,460],{"key":20,"text":455,"correct":22},"保险责任开始日期，以投保工程动工之日或保险财产运到工地之日，以后发生为准",{"key":24,"text":457,"correct":22},"试车考核期的保险责任一般不超过6 个月",{"key":27,"text":459,"correct":22},"保证期自工程验收合格或工程所有人使用时开始，以后发生者为准",{"key":31,"text":461,"correct":29},"对已使用的机械设备不负责试车，不承保保证期责任",{"id":463,"libraryId":5,"type":15,"typeLabel":16,"stem":464,"options":465,"answer":31,"analysis":33},908703,"某技术方案由三个投资者共同投资，若要比较三个投资者的财务内部收益率是否均衡，则适宜采用的现金流量表是（ ）。",[466,468,470,472],{"key":20,"text":467,"correct":22},"投资现金流量表",{"key":24,"text":469,"correct":22},"资本金现金流量表",{"key":27,"text":471,"correct":22},"财务计划现金流量表",{"key":31,"text":473,"correct":29},"投资各方现金流量表",{"id":475,"libraryId":5,"type":15,"typeLabel":16,"stem":476,"options":477,"answer":31,"analysis":33},908704,"某项目在经营年度外购原材料、燃料和动力费为1500 万元，工资及福利费为500 万元，修理费为50 万元，其他费用为40 万元，折旧费50 万元，摊销费40 万元，财务费用40 万元，则该项目年度经营成本为（ ）万元。",[478,480,482,484],{"key":20,"text":479,"correct":22},"1600",{"key":24,"text":481,"correct":22},"1640",{"key":27,"text":483,"correct":22},"1650",{"key":31,"text":485,"correct":29},"2090",{"id":487,"libraryId":5,"type":15,"typeLabel":16,"stem":488,"options":489,"answer":27,"analysis":33},908705,"某建设单位为了明确在特定融资方案下投资者权益投资的获利能力，就以投资方案资本金作为计算基础，把资本金偿还和利息支付作为现金流出，该单位编制的现金流量表是（ ）。",[490,491,492,493],{"key":20,"text":467,"correct":22},{"key":24,"text":473,"correct":22},{"key":27,"text":469,"correct":29},{"key":31,"text":471,"correct":22},{"id":495,"libraryId":5,"type":15,"typeLabel":16,"stem":496,"options":497,"answer":20,"analysis":33},908706,"某技术方案估计年总成本费用为8000 万元，其中外购原材料、燃料及动力费为4500 万元，折旧费为800 万元，摊销费为200 万元，修理费为500 万元，利息支出为210 万元。则该技术方案的年经营成本为（ ）万元。",[498,500,502,504],{"key":20,"text":499,"correct":29},"6790",{"key":24,"text":501,"correct":22},"4500",{"key":27,"text":503,"correct":22},"6290",{"key":31,"text":505,"correct":22},"7290",{"id":507,"libraryId":5,"type":15,"typeLabel":16,"stem":508,"options":509,"answer":20,"analysis":33},908707,"对于工程量较小、工艺较简单，且审查精度要求高的工程，适宜采用的审查方法是（ ）",[510,512,514,516],{"key":20,"text":511,"correct":29},"全面审查法",{"key":24,"text":513,"correct":22},"标准预算审查法",{"key":27,"text":515,"correct":22},"对比审查法",{"key":31,"text":517,"correct":22},"重点审查法",{"id":519,"libraryId":5,"type":15,"typeLabel":16,"stem":520,"options":521,"answer":27,"analysis":33},908708,"施工图预算审查方法中，审查速度快但审查精度较差的是（ ）",[522,523,524,526],{"key":20,"text":513,"correct":22},{"key":24,"text":515,"correct":22},{"key":27,"text":525,"correct":29},"分组计算审查法",{"key":31,"text":511,"correct":22},{"id":528,"libraryId":5,"type":15,"typeLabel":16,"stem":529,"options":530,"answer":27,"analysis":33},908710,"除专用合同条款另有约定外，《标准施工招标文件》中关于合同文件解释先后顺序的排列，下列说法中正确的是（ ）。",[531,533,535,537],{"key":20,"text":532,"correct":22},"合同协议书－专用条款－通用条款－中标通知书－投标函及投标函附录",{"key":24,"text":534,"correct":22},"合同协议书－中标通知书－专用条款－通用条款－投标函及投标函附录",{"key":27,"text":536,"correct":29},"合同协议书－中标通知书－投标函及投标函附录－专用条款－通用条款",{"key":31,"text":538,"correct":22},"合同协议书－专用条款－中标通知书－投标函及投标函附录－通用条款",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":27,"analysis":33},908711,"下列关于不平衡报价法的说法中，错误的说法是（ ）。",[543,545,547,549],{"key":20,"text":544,"correct":22},"能够早日结算的项目，可以适当的提高报价，后期工程项目的报价可适当降低",{"key":24,"text":546,"correct":22},"经核算，预计今后工程量会增加的项目，可适当提高报价",{"key":27,"text":548,"correct":29},"设计图纸不明确、估计修改后工程量要增加的项目，应适当降低单价",{"key":31,"text":550,"correct":22},"单价与包干混合制合同中，招标人要求有些项目采用包干报价时，宜报高价",{"id":552,"libraryId":5,"type":15,"typeLabel":16,"stem":553,"options":554,"answer":27,"analysis":33},908712,"某企业固定资产原价为10000 元，预计净残值600 元，预计可使用5 年。采用平均年限法计算第4 年的折旧额分别为（ ）元。",[555,557,559,561],{"key":20,"text":556,"correct":22},"1900",{"key":24,"text":558,"correct":22},"2000",{"key":27,"text":560,"correct":29},"1880",{"key":31,"text":562,"correct":22},"830",{"id":564,"libraryId":5,"type":15,"typeLabel":16,"stem":565,"options":566,"answer":31,"analysis":33},908713,"各年折旧基数不变，但折旧率逐年递减的固定资产折旧方法是（ ）。",[567,569,571,573],{"key":20,"text":568,"correct":22},"平均年限法",{"key":24,"text":570,"correct":22},"工作量法",{"key":27,"text":572,"correct":22},"双倍余额递减法",{"key":31,"text":574,"correct":29},"年数总和法",{"id":576,"libraryId":5,"type":15,"typeLabel":16,"stem":577,"options":578,"answer":27,"analysis":33},908714,"下列关于FIDIC《土木工程施工合同条件》争端解决的描述不正确的是（ ）。",[579,581,583,585],{"key":20,"text":580,"correct":22},"争端应提交争端裁决委员会是根据投标书附录中的规定由合同双方共同设立的",{"key":24,"text":582,"correct":22},"如果投标书附录中没有注明成员的数目，且合同双方没有其他协议，则DAB 应包含3 名成员",{"key":27,"text":584,"correct":29},"合同双方应当共同商定对成员的支付条件，并由责任方支付酬金",{"key":31,"text":586,"correct":22},"DAB 在收到书面报告后84 天内对争端作出裁决，并说明理由",{"id":588,"libraryId":5,"type":15,"typeLabel":16,"stem":589,"options":590,"answer":31,"analysis":33},908715,"某公司2015 年3 月份新增一项固定资产，4 月份安装调试完成，5 月份投入使用，11 月份停止使用。该项固定资产应从当年（ ）月份停止计提折旧。",[591,593,595,597],{"key":20,"text":592,"correct":22},"5",{"key":24,"text":594,"correct":22},"6",{"key":27,"text":596,"correct":22},"11",{"key":31,"text":598,"correct":29},"12",{"id":600,"libraryId":5,"type":15,"typeLabel":16,"stem":601,"options":602,"answer":27,"analysis":33},908716,"某项固定资产原值为50000 元，预计使用年限为6 年。预计净残值为2000 元，采用年数总和法进行折旧时，第3 年的折旧额为（ ）元。",[603,605,607,609],{"key":20,"text":604,"correct":22},"6257",{"key":24,"text":606,"correct":22},"6000",{"key":27,"text":608,"correct":29},"9143",{"key":31,"text":610,"correct":22},"9520",[612,615,618,621,624,627],{"id":15,"name":613,"category":7,"favorite":614},"领导干部任职前廉政法规知识测试题",92,{"id":616,"name":617,"category":7,"favorite":15},595,"建筑结构与设备",{"id":619,"name":620,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":622,"name":623,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":625,"name":626,"category":7,"favorite":8},534,"BIM工程师",{"id":628,"name":626,"category":7,"favorite":8},535]