[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910957,587,2,"多选题","（2018年考题）建设工程组织流水施工时,确定流水节拍的方法有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","定额计算法",true,{"key":16,"text":17,"correct":14},"B","经验估计法",{"key":19,"text":20,"correct":21},"C","价值工程法",false,{"key":23,"text":24,"correct":21},"D","ABC分析法",{"key":26,"text":27,"correct":21},"E","风险概率法","AB","流水节拍可分别按下列方法确定:1）定额计算法。2）经验估算法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]