[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910955":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910955,587,2,"多选题","（2015年考题）建设工程组织加快的成倍节拍流水施工的特点有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","各专业工作队在施工段上能够连续作业",true,{"key":16,"text":17,"correct":14},"B","相邻施工过程的流水步距均相等",{"key":19,"text":20,"correct":14},"C","不同施工过程的流水节拍成倍数关系",{"key":22,"text":23,"correct":24},"D","施工段之间可能有空闲时间",false,{"key":26,"text":27,"correct":14},"E","专业工作队数大于施工过程数","ABCE","本题考查的是流水施工的基本组织方式。成倍节拍流水施工特点：（1）同一施工过程在其各个施工段上的流水节拍均相等，不同施工过程的流水节拍不等，但其值为倍数关系；（2）相邻施工过程的流水步距相等，且等于流水节拍的最大公约数（K）；（3）专业工作队数大于施工过程数，即有的施工过程只成立一个专业工作队，而对于流水节拍大的施工过程，可按其倍数増加相应专业工作队数目；黑钻押题，金 考 典 软件考前更新，下载链接 www. jinkaodian. com （4）各个专业工作队在施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]