[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910948":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910948,587,2,"多选题","（2014年考题）建设单位编制的工程项目建设总进度计划包括的内容有（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","竣工投产交付使用计划表",false,{"key":16,"text":17,"correct":18},"B","工程项目一览表",true,{"key":20,"text":21,"correct":14},"C","年度建设资金平衡表",{"key":23,"text":24,"correct":18},"D","工程项目进度平衡表",{"key":26,"text":27,"correct":18},"E","投资计划年度分配表","BDE","工程项目建设总进度计划的表格部分包括工程项目一览表、工程项目进度平衡表、投资计划年度分配表和工程项目总进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]